Project/Work Description


UPC #118014

Rt 72 Manahawkin Bay Bridge, Contract 4
Contract 4 will include major Rehabilitation of the existing Route 72 Bridge over Manahawkin Bay . The entire existing superstructure for Bay Bridge will be removed and replaced, while retaining and rehabilitating the existing substructure. The superstructure width will be reduced as it will primarily be used for westbound traffic only. The project will also include the reconstruction of bridge approach roadways, bicycle and pedestrian accommodations, new storm drainage systems, ITS improvements, highway lighting, fender systems, bulkhead repairs, and utility relocations. The trestle bridge structure #1513-151 over Hillards Thorofare will also be rehabilitated under this contract.

Proposed Advertised Month August, 2016

Project Details

Ocean County/Stafford Twp

MP:  26.14-27.5

Estimate Range  over $10,000,000


UPC #113790

Rt 71, Main Ave to Cedar Ave, Pavement
This is a pavement reconstruction project. The project provides pavement rehabilitation in the municipalities of Neptune, Asbury Park, Loch Arbour and Allenhurst. The project also provides for the upgrade of 17 signalized intersections, and 12 unsignalized intersections to current ADA standards. In addition, the project provides for the repalcement of steel utility poles with standard wooden poles, and the relocation of private utility lines from State-owned facilities.

Proposed Advertised Month September, 2016

Project Details

Monmouth County/Asbury Park City, Neptune Twp, Loch Arbour Village

MP 7.87-9.92

Estimate Range  $5,000,001 - $10,000,000


UPC #960974

Rt 1&9 Haynes Avenue Operational Improvements
This project proposes a third lane and shoulder along Route 1&9 southbound between Haynes Avenue and the Anheuser-Busch entrance ramp. Also a roundabout is proposed on Haynes Avenue with a revised ramp to and from Route 1&9 and an access road to Bessemer Street under the Haynes Avenue Bridge.

Proposed Advertised Month September, 2016

Project Details

Essex County/Newark City

MP 46.5-47.69

Estimate Range  $5,000,001 - $10,000,000


UPC #138010

Rt 55 SB Schooner Landing Rd to Sherman Ave
Based on field testing, the proposed recommendation will include mill 2-3" / pave 2-3" and mill 2" / pave 3" on the mainline, shoulders and ramps; with some areas of Full Depth Reclamation (FDR) using cement on the outside shoulders.  Five structures included in project are: 0609-152, 0609-154, 0609-156, 0609-158, 0609-160

Proposed Advertised Month September, 2016

Project Details

Cumberland County/Millville City, Vineland City

MP: 21.8-26.5

Estimate Range  $1,000,001 - $5,000,000


UPC #113020

Rt 295/42/I-76, Direct Connect, Contract 3
This project will relieve the existing bottleneck at the interchange by constructing a direct connection on I-295 and other highway improvements that will reduce congestion and enhance traffic operations and safety throughout the project area. The improvements include a six lane mainline through the interchange, elimination of dangerous merging and weaving movements, upgrades to ramp geomerty and the addition of shoulders throughout the interchange.

Contract 3 will include the completion of the new I-295 NB and SB structures over I-76, Route 42, Ramps C and E, and Browning Road; the new Ramp A (Route 42 NB to I-295 NB) bridge will be completed under this contract along with a portion of Ramp F (I-76 EB to I-295 SB); and the new I-295 SB direct connection and Ramp A will be opened to traffic upon completion of this contract.

Proposed Advertised Month September, 2016

Project Details

Camden County/Bellmawr Boro

MP Rt 295: 26.41-27.8; Rt 42:  14-14.28

Estimate Range  over $100,000,000


UPC #124230

Rt 57, Port Murray Rd (CR 629) to Claremont Rd

Resurfacing Project Rt 57 EB & WB from Point Mountain Road (CR 629) to Claremont Rd., Mansfield Twp. Warren County. MP 14.52-18.70. This project's ranking in the Pavement Management System warranted resurfacing.

Proposed Advertised Month September, 2016

Project Details

Warren County/Mansfield Twp

MP 14.5-18.7

Estimate Range  $1,000,001 - $5,000,000


UPC #083480

Rt 23 over Branch of Wallkill River
Full replacement of Rt 23 Bridge (Structure # 1904-153) over Branch of Wallkill River

Proposed Advertised Month October, 2016

Project Details

Sussex County/Wantage Twp

MP 37.5-37.67

Estimate Range  $1,000,001 - $5,000,000


UPC #143620

Rt 322, Rt 47 (Delsea Dr) to Curtis Ave
Limited Scope pavement resurfacing, safety and ADA improvements along US Route 322 from MP 18.25 to MP 24.09 Structure # 0826150 - Rte. 322 Over 'Scotland Run'

Proposed Advertised Month October, 2016

Project Details

Gloucester County/Glassboro Boro, Monroe Twp

MP 18.25-24.09

Estimate Range  $1,000,001 - $5,000,000


UPC #123630

Rt 280 WB over Passaic Rvr & Proposed Essex County Park Rd
Limited scope Bridge Deck Replacements for Route 280 WB over Passaic River and Proposed Essex County Park Road. Structures 1418-155 and 0728-151.

Proposed Advertised Month October, 2016

Project Details

Essex & Union Counties/Roseland Boro, East Hanover Twp

MP 3.37

Estimate Range  $5,000,001 - $10,000,000


UPC #154450

Rt 80, Interchange 12 & 53 Ramps

Ramps along I-80 at Interchanges 12 & 53 have been identified as a Spot Location Project for the installation of High Friction Surface Treatment (HFST). This is a Pilot Project.

Proposed Advertised Month October, 2016

Project Details

Warren & Passaic Counties/Hope Twp, Wayne Twp

MP 12.03 & 53.62

Estimate Range  $1,000,001 - $5,000,000


UPC #153660

Rt 46, Teaneck Rd (CR 39) to Rt 1&9
This is Preventative Maintenance; a pavement resurfacing project that includes milling and resurface with 3" of HMA and other material.

Proposed Advertised Month October, 2016

Project Details

Bergen County/Ridgefield Park Village, Ridgefield Boro, Palisades Park Boro

MP: 70.8-72.09

Estimate Range  $1,000,001 - $5,000,000


UPC #114170

Rt 206, Hi Glen Dr to High St
Resurfacing of Rt 206 from just north of Lackawanna Drive in Byram Twp. to south of High Street in Andover Boro, Sussex County. (MP 99.60 to MP 103.02) Structures: 1911- 152, 153, 154, 155 (No work included for structures)

Proposed Advertised Month October, 2016

Project Details

Sussex County/Byram Twp

MP: 99.60-103.02

Estimate Range  $1,000,001 - $5,000,000


UPC #124370

Rt 27 Grand St NB Intersection
Project Improvements will include full traffic signal replacement with pedestrian accommodations, signing upgrades and reconstruction of all curb ramps to meet ADA compliant standards. Milling and paving within the intersection limits and improved crosswalk markings will also be included.

Proposed Advertised Month October, 2016

Project Details

Union County/Elizabeth City

MP: 33.96

Estimate Range  $1,000,001 - $5,000,000


UPC #143690

Rt 10, CR 508 (W Northfield Ave) to Merklin Ave/Kelley Dr
This is a resurfacing project in Livingston and West Orange townships. The project limits are from MP 18.8- 21.8. The project will follow Limited Scope delivery process.

Proposed Advertised Month October, 2016

Project Details

Essex County/Livingston Twp, West Orange Twp

MP: 18.8-21.8

Estimate Range  $1,000,001 - $5,000,000


UPC #163540

Rt 206, Bridges over Stony Brook - PRIORITY
Rt 206, Bridges over Stony Brook, Priority Rehabilitation and Replacement, is located in Princeton Township, at MP 52.4 - 52.6. The structure # 1129-155, is a historic bridge. It needs priority rehabilitation after a portion of the stone railing on the historic bridge collapsed on the southbound side. The structure #1129-154 is in poor condition and needs priority replacement.

Proposed Advertised Month November, 2016

Project Details

Mercer County/Princeton Twp

Estimate Range  $20,000,001 - $40,000,000


UPC #103830

Rt 94 Black Creek Tributary, Culvert Replacement
Culvert replacement, Structure #1910-152, SR:23.2. Project to be funded under Culvert Replacement line item.

Proposed Advertised Month November, 2016

Project Details

Sussex County/Vernon Twp

MP: 38.79-38.84

Estimate Range  $1,000,001 - $5,000,000


UPC #143710

Rt 152, Bay Ave to Seaview Dr
2017 TTF resurfacing project.  Structures: 0122-159, 0122-158, 0122-157, 0122-156, 0122-155, 0122-153

Proposed Advertised Month November, 2016

Project Details

Atlantic County/Somers Point City, Egg Harbor Twp

MP: 0.0-3.16

Estimate Range  $5,000,001 - $10,000,000


UPC #143740

Rt 47, CR 552 (W Sherman Ave) to Rt 56 (Landis Ave)
TTF 2017 Pavement Resurfacing Project

Proposed Advertised Month December, 2016

Project Details

Cumberland County/Vineland City

MP: 43.85-46.6

Estimate Range  $1,000,001 - $5,000,000


UPC #153620

Rt 94, Road to Hospital to Rt 206
Pavement Resurfacing Project of Route 94 (MP 21.70 to MP 22.47) Road to Hospital to Route 206 in Newton town and Fredon Township, in Sussex County.

Proposed Advertised Month December, 2016

Project Details

Sussex County/Newton Town

MP 21.70-22.47

Estimate Range  $1,000,001 - $5,000,000


UPC #143340

Rt 15 NB, Bridge over Lake Hopatcong

The replacement of the deck of the Rt 15 NB bridge over Lake Hopatcong, and the construction of scour countermeasures to address this scour critical structure.

Proposed Advertised Month December, 2016

Project Details

Morris County/Jefferson Twp

MP 6.7

Estimate Range  $1,000,001 - $5,000,000


UPC #983420

Bloomfield Avenue Bridge

This is a Bridge Rehabilitation project that includes super structure of the Bloomfield Avenue Bridge over NJ Transit (Structure No. 0764-152) to be replaced and repairs made to the substructure. The work will also include the improvement of both roadway approaches and the retaining wall leading to the bridge from the intersection with Maple Avenue/Pine Street.

Proposed Advertised Month December, 2016

Project Details

Essex County/Glen Ridge Twp, Montclair Twp

MP 7-7.1

Estimate Range  $1,000,001 - $5,000,000


UPC #960596

Rt 206 (41) Crusers Brook Bridge

The existing Route 206 bridge over Crusers Brook will be demolished and replaced with a new structure.

Proposed Advertised Month December, 2016

Project Details

Somerset County/Montgomery Twp

MP 61.64-62.1

Estimate Range  $1,000,001 - $5,000,000


UPC #093270

Rt 168 Bridge over Big Timber Creek

This project will replace the existing bridge on Rt. 168 over Big Timber Creek.  Structure #0819-150

Proposed Advertised Month December, 2016

Project Details

Gloucester & Camden Counties/Washington Twp, Gloucester Twp

MP 0.75

Estimate Range  $5,000,001 - $10,000,000


UPC #124270

Rt 72, Ash Road to Marsha Drive

This is a Limited Scope Pavement Resurfacing Project. MP 18.5 - 21.73 and MP 22.54 - 25.38

Proposed Advertised Month December, 2016

Project Details

Ocean County/Stafford Twp

MP 18.5-25.38

Estimate Range  $5,000,001 - $10,000,000


UPC #153680

Rt 17 NB, Linwood Ave to Lake St
This is Preventative Maintenance; a pavement resurfacing project that includes milling and resurface with 3" of HMA and other material.

Proposed Advertised Month January, 2017

Project Details

Bergen County/Ridgewood Village, Saddle River Boro, Ramsey Boro

MP 16.48-22.8

Estimate Range  $1,000,001 - $5,000,000


UPC #123270

Pulaski Contract #5

This project will rehabilitate the two center ramps (Broadway and Kearny) on the Pulaski Skyway . Includes deck replacement of the ramps and rehabilitation of steel superstructure.

Proposed Advertised Month January, 2017

Project Details

Hudson & Essex Counties/Jersey City, Kearny Town, Newark City

MP 51-54.5

Estimate Range  $10,000,001 - $20,000,000


UPC #153640

Rt 159, Rt 46 to Plymouth St (CR 627)

Limited Scope in-house design TTF Resurfacing project. Route 159 from milepost 0.0 to milepost 1.36.

Proposed Advertised Month January, 2017

Project Details

Essex & Morris Counties/Fairfield Twp, Montville Twp

MP 0.0-1.36

Estimate Range  $1,000,001 - $5,000,000


UPC #153670

Rt 82, Rt 124 to Rt 439

This is a Limited Scope State funded 2018 TTF Resurfacing project between MP 0.0 to MP 1.87 and MP 4.0 to MP 4.92. The project will be ADA compliant.

Proposed Advertised Month January, 2017

Project Details

Union County/Springfield Twp, Union Twp

MP 0.0-4.92

Estimate Range  $1,000,001 - $5,000,000


UPC #123900

Rt 78 Pattenburg Rd (CR 614) over Rt 78

The existing bridge superstructure on the Pattenburg Road (614) bridge over I-78 will be replaced and there will be repairs made to the bridge abutment. The bridge superstructure rating is 4 (Poor) and the bridge sufficiency rating is 78.20. The structure is located at I-78 milepost 11.76 in Union Township, Hunterdon County.

Proposed Advertised Month January, 2017

Project Details

Hunterdon County/Union Twp

MP 11.57-11.95

Estimate Range  $1,000,001 - $5,000,000


UPC #113530

Rt 173 Musconetcong River, Culvert Replacement

This is a culvert replacement project identified by the Bridge Management System. Rehabilitation/replacement of deteriorated culvert. The existing culvert is comprised of a single span reinforced concrete culvert at the north side linked to two corugated metal pipe arches at the south side. The structure is rated 4 (poor) in the last inspection report mostly due to the severe corrosion section loss in the bottom plates in both pipe arches.

Proposed Advertised Month January, 2017

Project Details

Hunterdon County/Bethlehem Twp

MP 6.81-6.99

Estimate Range  $1,000,001 - $5,000,000

Operations

Project/Work Description

 

DP #15468

Maintenance Timber/Underwater/Drainage Structural Repair Contract, Central - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in Central Region/Hunterdon, Mercer, Middlesex, Monmouth, Ocean, Somerset & Warren Counties

Estimate Range $1,000,000 - $5,000,000


DP #15469

Maintenance Timber/Underwater/Drainage Structural Repair Contract, South - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in South Region/Atlantic, Burlington, Camden, Cape May, Cumberland, Gloucester & Salem Counties

Estimate Range $1,000,000 - $5,000,000


DP #16409

Re-Advertisement Maintenance Beam Guide Rail & Attenuator Repair Contract, North - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in North Region/Bergen, Essex, Hudson, Morris, Passaic, Sussex, Union & Warren Counties

Estimate Range $1,000,000 - $5,000,000


DP #16410

Re-Advertisement Maintenance Beam Guide Rail & Attenuator Repair Contract, Central - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in Central Region/Hunterdon, Mercer, Middlesex, Monmouth, Ocean, Somerset & Warren Counties

Estimate Range $1,000,000 - $5,000,000


DP #15438

Maintenance Bridge Painting Contract 2016 - 2

Proposed Advertised Month August, 2016

Project Details

Twenty-three (23) Bridges Route 18; Colts Neck Township, East Brunswick Township, Eatontown Borough, Marlboro Township, New Brunswick City, Ocean Township, Piscataway Township/Middlesex & Monmouth Counties

Estimate Range   over $10,000,000


DP #15473

Maintenance Machine Sweeping Contract, Statewide - 2016

Proposed Advertised Month August, 2016

Project Details

Statewide/Statewide/Statewide

Estimate Range $5,000,000 - $10,000,000


DP #15451

Maintenance Hot Mix Asphalt Pavement Repair Contract, North - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in North Region/Bergen, Essex, Hudson, Morris, Passaic, Sussex, Union & Warren Counties

Estimate Range $1,000,000 - $5,000,000


DP #15452

Maintenance Hot Mix Asphalt Pavement Repair Contract, Central - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in Central Region/Hunterdon, Mercer, Middlesex, Monmouth, Ocean, Somerset & Warren Counties

Estimate Range $1,000,000 - $5,000,000


DP #15453

Maintenance Hot Mix Asphalt Pavement Repair Contract, South - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in South Region/Atlantic, Burlington, Camden, Cape May, Cumberland, Gloucester & Salem Counties

Estimate Range $1 - $1,000,000


DP #15454

Maintenance Long-Life Pavement Markings Contract, North - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in North Region/Bergen, Essex, Hudson, Morris, Passaic, Sussex, Union & Warren Counties

Estimate Range $1 - $1,000,000


DP #15455

Maintenance Long-Life Pavement Markings Contract, Central - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in Central Region/Hunterdon, Mercer, Middlesex, Monmouth, Ocean, Somerset & Warren Counties

Estimate Range $1 - $1,000,000


DP #15456

Maintenance Long-Life Pavement Markings Contract, South - 2016

Proposed Advertised Month August, 2016

Project Details

Various Locations/Various municipalities in South Region/Atlantic, Burlington, Camden, Cape May, Cumberland, Gloucester & Salem Counties

Estimate Range $1 - $1,000,000


DP #15435

Maintenance Roadway Repair Contract, Central, Sub-Region C-3, Contract No. C308

Proposed Advertised Month August, 2016

Project Details

Route 33 EB MP 28.90 - 31.10, Route 33 WB MP 29.16 - 31.10, Route 34 MP 0.0 - 0.15, NB MP 0.15 - 4.1, SB MP 0.15 - 1.61, MP 10.3 - 13.0, Route 88 MP 0.0 - 2.0, Route 166 MP 0.0 - 1.85/Beachwood Borough, Colts Neck Township, Freehold Township, Howell Township, Lakewood Township, South Toms River Borough, Toms River Township/Monmouth & Ocean Counties

Estimate Range $1 - $1,000,000


DP #15436

Maintenance Resurfacing Route 9 Northbound and Southbound; Contract #130123940

Proposed Advertised Month August, 2016

Project Details

US 9 (MP 130.93 - 131.87) from North of Kearney Road to Ellis S. Vieser/Thomas Edison Bridge/Sayreville Borough/Middlesex County

Estimate Range $1,000,000 - $5,000,000


DP #15434

Maintenance Roadway Repair Contract, Central, Sub-Region C-1, Contract No. C108

Proposed Advertised Month August, 2016

Project Details

Route 29 NB MP 6.48 - 8.5, SB MP 6.24 - 8.5, Both MP 9.4 - 13.10, US 202 NB MP 7.04 - 9.36/East Amwell Township, Ewing Township, Hopewell Township, Raritan Township, Trenton City/Hunterdon & Mercer Counties

Estimate Range $5,000,000 - $10,000,000


DP #16417

Maintenance Orphan Bridge Repair Contract 2016

Proposed Advertised Month August, 2016

Project Details

To be determined

Estimate Range $1,000,000 - $5,000,000


DP #15474

Drainage Restoration Contract, North - 2016

Proposed Advertised Month January, 2017

Project Details

Various Locations/Various municipalities in North Region/Bergen, Essex, Hudson, Morris, Passaic, Sussex, Union & Warren Counties

Estimate Range $1,000,000 - $5,000,000


DP #15475

Drainage Restoration Contract, Central - 2016

Proposed Advertised Month January, 2017

Project Details

Various Locations/Various municipalities in Central Region/Hunterdon, Mercer, Middlesex, Monmouth, Ocean, Somerset & Warren Counties

Estimate Range $1,000,000 - $5,000,000


DP #15476

Drainage Restoration Contract, South - 2016

Proposed Advertised Month January, 2017

Project Details

Various Locations/Various municipalities in South Region/Atlantic, Burlington, Camden, Cape May, Cumberland, Gloucester & Salem Counties

Estimate Range $1,000,000 - $5,000,000


 
Go to NJDOT home page Contact Us | Privacy Notice | Legal Statement | Accessibility Statement  Go to State of New Jersey home page
  department: home | about | NJ commuter | in the works | business | engineering | freight, air & water | capital | community | data | links | index
  statewide: NJ Home | about NJ | business | government | state services A to Z | departments

  Copyright © State of New Jersey, 2002-2016
  Department of Transportation
  P.O. Box 600
  Trenton, NJ 08625-0600
OPRA - open public records act

  Last Updated:  August 4, 2016